Screenhouse and Chlorine Building Upgrades
Carbonear, Newfoundland and Labrador
Federal contribution
$101,449
Federal share40%
of $253.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
202420252026
BuiltForecast
Approved 17 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Carbonear
- Construction start
- Apr 5, 2026(forecast)
- Construction end
- May 17, 2026(forecast)
Also in Carbonear
- Upgrades to Route 70- Interchange at Valley Road and Route 75 - Veterans Memorial Highway$2.2M
- Water System Upgrading$807.0K
- Adelaide Street Water Sewer Storm Street Upgrades Ph2$587.6K
- Water Street Water, Sewer and Street Upgrading$517.8K
- Water Street - Water, Sewer and Street Upgrading Phase 3$473.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67662 in the federal list. How to read these figures.