Beach Road Sewer Sizing Upgrade

Carbonear, Newfoundland and Labrador

underwayWastewaterGIS
Federal contribution
$174,399
Federal share40%

of $436.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 5, 2024
20242025
BuiltForecast

Approved 17 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carbonear
Construction start
Aug 25, 2025(actual)
Construction end
Nov 14, 2025(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 8, 2025

Also in Carbonear

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67664 in the federal list. How to read these figures.