Conklin Water Treatment Plant Upgrades-Construction

Wood Buffalo (Regional Municiaplity), Alberta

completeDrinking WaterCVRIS
Federal contribution
$3.1M
$3,089,600
Federal share80%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2025
20242025
Built

Approved 23 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 26, 2023(actual)
Construction end
Apr 14, 2025(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 31, 2023
  • Construction end12 months earlyforecast Mar 31, 2026