Water and Sewer Upgrading - Shaheen Crescent - Phase 2
Come By Chance, Newfoundland and Labrador
Federal contribution
$360,920
Federal share40%
of $902.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
20242025
Built
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Come by Chance
- Construction start
- Jul 29, 2025(actual)
- Construction end
- Nov 14, 2025(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2025
- Construction end9 months earlyforecast Jul 31, 2026