Water and Sewer Upgrading - Shaheen Crescent - Phase 2

Come By Chance, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$360,920
Federal share40%

of $902.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
20242025
Built

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Come by Chance
Construction start
Jul 29, 2025(actual)
Construction end
Nov 14, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast May 15, 2025
  • Construction end9 months earlyforecast Jul 31, 2026

Also in Come By Chance

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67705 in the federal list. How to read these figures.