Wastewater System Improvements
Come By Chance, Newfoundland and Labrador
Federal contribution
$77,103
Federal share36%
of $212.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Come by Chance
- Construction start
- Nov 14, 2017(actual)
- Construction end
- Dec 3, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 5, 2017
- Construction end2 months lateforecast Oct 1, 2019
Also in Come By Chance