ECC - SD 83 - Highland Park Elementary Ventilation Improvements

Armstrong, British Columbia

completeVentilationCVRIS
Federal contribution
$556,339
Federal share80%

of $695.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
2024
Built

Approved 10 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2023(actual)
Construction end
Dec 1, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2023