Wastewater Treatment Plant Rehabilitation
Federal contribution
$316,500
Federal share50%
of $633.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Armstrong
- Construction start
- Sep 18, 2017(actual)
- Construction end
- Jul 13, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 15, 2017
- Construction end3 months lateforecast Mar 31, 2018
Also in Armstrong