The Elliott Community Long Term Care Residence - HVAC upgrade
Federal contribution
$210,450
Federal share80%
of $263.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2024
202420252026
Built
Approved 18 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Elliott Community
- Construction start
- Apr 21, 2025(actual)
- Construction end
- Dec 22, 2025(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 3, 2025
Also in Guelph