St. Joseph's Villa of Sudbury - LTCH Dry Sprinkler Repairs

Greater Sudbury, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$355,619
Federal share80%

of $444.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2024
20242025
Built

Approved 18 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 28, 2024(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction start13 months lateforecast Sep 30, 2023
  • Construction end12 months earlyforecast Dec 31, 2025

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67938 in the federal list. How to read these figures.