West Park Long Term Care Centre- Replace Air Handling Unit #1, #2, #4 and #5

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$1.8M
$1,794,362
Federal share80%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2023
202420252026
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 1, 2024(actual)
Construction end
Nov 30, 2025(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2023
  • Construction end4 weeks earlyforecast Dec 31, 2025

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67943 in the federal list. How to read these figures.