Transit Terminal Upgrades
Federal contribution
$155,825
Federal share50%
of $311.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2025
today
20242025202620272028
BuiltForecast
Approved 2.1 years before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of North Bay
- Construction start
- Apr 1, 2025(actual)
- Construction end
- Mar 31, 2028(forecast)