Refurbishment of 40 foot Conventional Diesel Buses
Federal contribution
$432,684
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2025
202420252026
BuiltForecast
Approved 2.1 years before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Regional Municipality of Niagara
- Construction start
- Mar 18, 2025(actual)
- Construction end
- Mar 31, 2026(forecast)
Also in Niagara
- Regional Municipality of Niagara Bus Fleet Replacement$37.0M
- Replacement of 60 foot Conventional Diesel Buses$3.2M
- Replacement of Specialized/ ParaTransit Buses$2.8M
- Niagara Falls Water Treatment Plant Lead Abatement & Filter Repairs (Plant 1 & 2)$1.9M
- Facility, Strategic Asset and Service Network Review and Facility Capital Investments$1.9M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68047 in the federal list. How to read these figures.