Transit Stop Upgrades
Federal contribution
$920,000
Federal share40%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 12, 2024
today
2024202620282030
BuiltForecast
Approved 14 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Peterborough
- Construction start
- Jul 8, 2024(actual)
- Construction end
- Mar 31, 2031(forecast)
Against the original forecast
- Construction start5 weeks lateforecast May 31, 2024
Also in Peterborough
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68059 in the federal list. How to read these figures.