Back to projects

Construction of Carrefour International Brian-Mulroney at Université Laval

Québec, Quebec

approvedEducation, Training and ChildcareCCRIS
Federal contribution
$25.0M
$25,000,000
Federal share53%

of $47.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2023
today
20242025202620272028
BuiltForecast

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Université Laval
Construction start
Sep 15, 2026(forecast)
Construction end
Jun 9, 2028(forecast)

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68095 in the federal list. How to read these figures.