approvedOtherGICB
Federal contribution
$25.0M
$25,000,000
Federal share23%

of $107.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2024
20252026
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
City of Toronto
Construction start
Mar 29, 2024(forecast)
Construction end
Mar 31, 2026(forecast)