7projects·$13.2Mfederal of $21.5M eligible
Rehabilitation of Vendôme Platform McGill University Health Centre
$157.6KMontréal · Public Transit
complete·approved 2017
Redevelopment and renovation (Lot 1) of the Wilson Hall Pavilion
$1.2MMontréal · Education, Training and Childcare
complete·approved 2021
Electrical Distribution Change at Burnside Pavilion (Data Center)
$1.2MMontréal · Education, Training and Childcare
complete·approved 2021
Envelope, Roof and Terraces Repairs (3 of 3) at the Education Building
$1.7MMontréal · Education, Training and Childcare
complete·approved 2021
Envelope Restoration (1 and 2 of 3) of the Strathcona Music Building
$2.6MMontréal · Education, Training and Childcare
complete·approved 2021
Renovation of the teaching rooms at Burnside Pavilion of McGill University
$2.8MMontréal · Education, Training and Childcare
complete·approved 2022
Transformer and Cooling Towers Replacement at McIntyre Hall
$3.6MMontréal · Ventilation
complete·approved 2021
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Rehabilitation of Vendôme Platform McGill University Health Centre Réseau de transport métropolitain (RTM) | Montréal | Public Transit | complete | $157.6K | $315.1K | 2017 |
| Redevelopment and renovation (Lot 1) of the Wilson Hall Pavilion McGill University | Montréal | Education, Training and Childcare | complete | $1.2M | $3.1M | 2021 |
| Electrical Distribution Change at Burnside Pavilion (Data Center) McGill University | Montréal | Education, Training and Childcare | complete | $1.2M | $1.6M | 2021 |
| Envelope, Roof and Terraces Repairs (3 of 3) at the Education Building McGill University | Montréal | Education, Training and Childcare | complete | $1.7M | $2.1M | 2021 |
| Envelope Restoration (1 and 2 of 3) of the Strathcona Music Building McGill University | Montréal | Education, Training and Childcare | complete | $2.6M | $4.3M | 2021 |
| Renovation of the teaching rooms at Burnside Pavilion of McGill University McGill University | Montréal | Education, Training and Childcare | complete | $2.8M | $4.9M | 2022 |
| Transformer and Cooling Towers Replacement at McIntyre Hall McGill University | Montréal | Ventilation | complete | $3.6M | $5.2M | 2021 |