2projects·$25.9Mfederal of $57.4M eligible
Strategic Highway System: Provincial Trunk Highway (PTH) 2 and PTH 3 Rehabilitation
$25.7MCarman +2 · Highways and Roads
complete·approved 2018
Fannystelle Wastewater System
$219.0KFannystelle≈ · Wastewater
complete·approved 2007
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Strategic Highway System: Provincial Trunk Highway (PTH) 2 and PTH 3 Rehabilitation Manitoba Strategic Infrastructure Secretariat | Carman +2 more | Highways and Roads | complete | $25.7M | $56.4M | 2018 |
| Fannystelle Wastewater System Rural Municipality of Grey | Fannystelle≈ | Wastewater | complete | $219.0K | $977.1K | 2007 |