2projects·$39.8Mfederal of $100.1M eligible
Modification of Hydro-Québec's facilities in Inukjuak to integrate and optimize the hydroelectricity generated from the Innavik power station
$34.5MInukjuak · Green Energy
complete·approved 2021
Conversion of heating systems in Inukjuaks social housing installations: from oil to a dual-energy heating system (electricity/fuel oil)
$5.3MInukjuak · Green Energy
complete·approved 2019
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Modification of Hydro-Québec's facilities in Inukjuak to integrate and optimize the hydroelectricity generated from the Innavik power station Hydro-Québec | Inukjuak | Green Energy | complete | $34.5M | $88.1M | 2021 |
| Conversion of heating systems in Inukjuaks social housing installations: from oil to a dual-energy heating system (electricity/fuel oil) Kativik Municipal Housing Bureau (KMHB) | Inukjuak | Green Energy | complete | $5.3M | $11.9M | 2019 |