Burnaby - Burnaby Lake Highway 1 Pedestrian Overpass

Burnaby, British Columbia

completeActive TransportationCCRIS
Federal contribution
$3.8M
$3,750,000
Federal share40%

of $9.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2021
20222023202420252026
Built
Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Burnaby
Construction start
Oct 6, 2023(actual)
Construction end
Mar 31, 2026(actual)

Against the original forecast

  • Construction start11 months earlyforecast Aug 30, 2024
  • Construction end2 months earlyforecast Jun 1, 2026