Combined Sewer Separation Program 2017

Burnaby, British Columbia

completeWastewaterCWWF
Federal contribution
$2.9M
$2,943,080
Federal share50%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Burnaby
Construction start
Aug 8, 2017(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast Aug 1, 2016
  • Construction end5 weeks lateforecast Apr 27, 2018

Also in Burnaby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49806 in the federal list. How to read these figures.