Brentwood Stationhouse Upgrade (South)
Federal contribution
$3.0M
$3,046,000
Federal share40%
of $7.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2022
2021202220232024
Built
Approved 14 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Province of British Columbia
- Construction start
- May 16, 2022(actual)
- Construction end
- Jan 2, 2024(actual)
Also in Burnaby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57933 in the federal list. How to read these figures.