Old Crow Community Centre Building Replacement

Vuntut Gwitchin First Nation, Yukon

completeCultureRNIS
Federal contribution
$5.0M
$5,000,000
Federal share75%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 19, 2019
202020212022
Built

Approved 6 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Government of Yukon
Construction start
Feb 17, 2020(actual)
Construction end
Nov 28, 2021(actual)

Against the original forecast

  • Construction end6 months lateforecast May 31, 2021