Old Crow Lagoon upgrades
Vuntut Gwitchin First Nation, Yukon
Federal contribution
$3.3M
$3,260,439
Federal share67%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 22, 2016
20172018201920202021
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Feb 20, 2019(actual)
- Construction end
- Dec 2, 2020(actual)
Against the original forecast
- Construction start3 months earlyforecast Jun 1, 2019
- Construction end4 months earlyforecast Mar 31, 2021