VGFN Elders Complex
Vuntut Gwitchin First Nation, Yukon
Federal contribution
$9.0M
$9,000,000
Federal share42%
of $21.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2021
202120222023
Built
Approved 8 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Vuntut Gwitchin Government
- Construction start
- Jun 6, 2022(actual)
- Construction end
- May 19, 2023(actual)
Against the original forecast
- Construction start17 months lateforecast Jan 4, 2021
- Construction end4 months lateforecast Jan 17, 2023