Reconstruction of Florence Street

Huntsville, Ontario

completeHighways and RoadsMRIF
Federal contribution
$325,125
Federal share33%

of $975.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Huntsville
Construction start
Apr 30, 2005(actual)
Construction end
Feb 14, 2007(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 31, 2006