Rehabilitation of downtown road infrastructure
Federal contribution
$121,338
Federal share33%
of $364.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Whitby
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Sep 29, 2008(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2004
- Construction end2 years lateforecast Sep 30, 2006
Also in Whitby
- Whitby Sports Complex$25.0M
- Ventilation Upgrade; Window Replacements; Exterior Door FOB Access; Water Bottle Filling and Hand Sanitizing Station; Childcare Vestibules; Plexiglass Partitions; Fencing$7.6M
- Outdoor Classrooms Replacement of Portable Classrooms$3.8M
- Waterfront Trail Redevelopment for Whitby, Ontario$2.6M
- Wireless Infrastructure Upgrade Project Group$2.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11429 in the federal list. How to read these figures.