Upgrading of Geraldton Sewage System

Geraldton, Ontario

completeWastewaterMRIF
Federal contribution
$3.1M
$3,129,100
Federal share33%

of $9.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Greenstone
Construction start
Apr 20, 2005(actual)
Construction end
May 16, 2007(actual)

Against the original forecast

  • Construction end17 months earlyforecast Sep 30, 2008