Rehabilitation of Airport Road
Federal contribution
$1.9M
$1,854,515
Federal share33%
of $5.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Greenstone
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Nov 20, 2015(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2016
Also in Geraldton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24634 in the federal list. How to read these figures.