Municipality of Greenstone Asset Management
Federal contribution
$5,055
Federal share33%
of $15.2K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 24, 2007
200720082009
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Greenstone
- Construction start
- Jun 1, 2007(actual)
- Construction end
- Mar 30, 2009(actual)
Also in Geraldton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18070 in the federal list. How to read these figures.