Back to projects

Municipality of Greenstone Asset Management

Geraldton, Ontario

completeCapacity BuildingMRIF
Federal contribution
$5,055
Federal share33%

of $15.2K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 24, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Greenstone
Construction start
Jun 1, 2007(actual)
Construction end
Mar 30, 2009(actual)

Also in Geraldton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18070 in the federal list. How to read these figures.