Brandon Keystone Centre Agricultural Centre of Excellence and Capital Upgrades

Brandon, Manitoba

completeTourismMRIF
Federal contribution
$6.1M
$6,091,243
Federal share33%

of $18.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2005
200520062007200820092010
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Jan 19, 2005(actual)
Construction end
Jul 12, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jan 1, 2005
  • Construction end21 months earlyforecast Mar 31, 2012