Flood Protection project in the City of Brandon
Federal contribution
$12.0M
$11,965,582
Federal share50%
of $23.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 18, 2014
2014201620182020
Built
Approved 2 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Brandon
- Construction start
- May 26, 2014(actual)
- Construction end
- Dec 21, 2020(actual)
Against the original forecast
- Construction start10 months earlyforecast Apr 1, 2015
Also in Brandon