Trans-Canada Highway - Highway 1 Paving (Eastbound Lanes PTH 21 to PTH 10)

Brandon, Manitoba

completeHighways and RoadsISF
Federal contribution
$4.3M
$4,257,521
Federal share41%

of $10.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 22, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Manitoba
Construction start
Jul 23, 2009(actual)
Construction end
Jun 1, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 1, 2009
  • Construction end6 weeks earlyforecast Jul 15, 2010

Also in Brandon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29511 in the federal list. How to read these figures.