Trans-Canada Highway - Highway 1 Paving (Eastbound Lanes PTH 21 to PTH 10)
Federal contribution
$4.3M
$4,257,521
Federal share41%
of $10.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- Jul 23, 2009(actual)
- Construction end
- Jun 1, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 1, 2009
- Construction end6 weeks earlyforecast Jul 15, 2010