New Winnipeg Humane Society Facility
Federal contribution
$1.0M
$1,000,000
Federal share12%
of $8.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Winnipeg Humane Society
- Construction start
- Apr 22, 2005(actual)
- Construction end
- Feb 11, 2008(actual)
Against the original forecast
- Construction start12 months earlyforecast Apr 26, 2006
- Construction end6 weeks lateforecast Dec 30, 2007