Crescent Lake Recreational Enhancements

Portage la Prairie, Manitoba

completeRecreationMRIF
Federal contribution
$120,000
Federal share17%

of $720.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 24, 2006
20062007
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Portage la Prairie
Construction start
Nov 17, 2005(actual)
Construction end
Mar 21, 2007(actual)

Against the original forecast

  • Construction end7 months earlyforecast Nov 1, 2007

Also in Portage la Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11693 in the federal list. How to read these figures.