Portage West Sewage Pumping Station
Federal contribution
$166,600
Federal share27%
of $625.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2005
200620072008
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Portage la Prairie
- Construction start
- May 17, 2005(actual)
- Construction end
- Feb 27, 2008(actual)
Against the original forecast
- Construction end7 months earlyforecast Oct 1, 2008
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11719 in the federal list. How to read these figures.