Improvements to the Ross Recycling Depot/Composting Area

Cobden, Ontario

completeSolid Waste ManagementMRIF
Federal contribution
$25,000
Federal share33%

of $75.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 28, 2005(actual)
Construction end
Feb 23, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 1, 2005
  • Construction end14 months lateforecast Dec 31, 2005

Also in Cobden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11728 in the federal list. How to read these figures.