Upgrading of Water Distribution System

Cobden, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$181,104
Federal share33%

of $543.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 1, 2010(actual)
Construction end
Jun 17, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 1, 2010
  • Construction end4 months earlyforecast Oct 31, 2011

Also in Cobden