Asset Management
Federal contribution
$4,347
Federal share33%
of $13.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 24, 2007
200720082009
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Whitewater Region
- Construction start
- Jun 1, 2007(actual)
- Construction end
- Jan 26, 2009(actual)
Against the original forecast
- Construction end2 months earlyforecast Mar 31, 2009
Also in Cobden
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17771 in the federal list. How to read these figures.