Back to projects

Replacement of Shewfelt Creek Bridge

Desbarats, Ontario

completeHighways and RoadsMRIF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Johnson
Construction start
Apr 20, 2005(actual)
Construction end
Mar 10, 2006(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast May 30, 2005
  • Construction end5 months lateforecast Sep 30, 2005

Also in Desbarats

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11800 in the federal list. How to read these figures.