Replacement of Shewfelt Creek Bridge
Federal contribution
$50,000
Federal share33%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Johnson
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Mar 10, 2006(actual)
Against the original forecast
- Construction start6 weeks earlyforecast May 30, 2005
- Construction end5 months lateforecast Sep 30, 2005
Also in Desbarats
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11800 in the federal list. How to read these figures.