Back to projects

Replacement of the Stewart Bridge

Kincardine, Ontario

completeHighways and RoadsMRIF
Federal contribution
$198,333
Federal share33%

of $595.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Kincardine
Construction start
Apr 20, 2005(actual)
Construction end
Aug 12, 2006(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 16, 2004
  • Construction end3 months earlyforecast Oct 31, 2006

Also in Kincardine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11979 in the federal list. How to read these figures.