Andrew Malcolm Drive Watermain Replacement

Kincardine, Ontario

completeDrinking WaterGIS
Federal contribution
$451,440
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
202320242025
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Municipality of Kincardine
Construction start
Jun 23, 2025(actual)
Construction end
Sep 8, 2025(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Oct 31, 2025

Also in Kincardine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62885 in the federal list. How to read these figures.