Andrew Malcolm Drive Watermain Replacement
Federal contribution
$451,440
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
202320242025
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Kincardine
- Construction start
- Jun 23, 2025(actual)
- Construction end
- Sep 8, 2025(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Oct 31, 2025