Kincardine to Inverhuron Provincial Park (KIPP) Trail

Kincardine, Ontario

completeRecreationCCRIS
Federal contribution
$435,120
Federal share31%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 8, 2021
20212022
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of Kincardine
Construction start
Apr 11, 2022(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Oct 15, 2022