Upgrading and replacement of infrastructure at Glendale Ave./ Merritt St.
Federal contribution
$2.4M
$2,370,050
Federal share33%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of St. Catharines
- Construction start
- Jun 1, 2005(actual)
- Construction end
- Sep 12, 2008(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2008
Also in St. Catharines
- St. Catharines Arts Centre$18.0M
- Carlisle Street Garage Replacement$9.3M
- HVAC; Handwashing and Washrooms; Online Learning Support; New Portable; Building Ventilation Controls; Creating New Classroom Space$7.8M
- Facility Expansion$3.9M
- Purchase three 60' buses and nine 40' buses to replace existing vehicles for conventional service$3.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12091 in the federal list. How to read these figures.