Upgrading and replacement of infrastructure at Glendale Ave./ Merritt St.

St. Catharines, Ontario

completeHighways and RoadsMRIF
Federal contribution
$2.4M
$2,370,050
Federal share33%

of $7.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of St. Catharines
Construction start
Jun 1, 2005(actual)
Construction end
Sep 12, 2008(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2008