Gladstone District Community Centre
Federal contribution
$250,000
Federal share17%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 14, 2007
200820092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Gladstone
- Construction start
- Feb 21, 2007(actual)
- Construction end
- Dec 4, 2009(actual)
Against the original forecast
- Construction start19 months lateforecast Jul 15, 2005
- Construction end11 months lateforecast Dec 31, 2008
Also in WestLake-Gladstone
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12111 in the federal list. How to read these figures.