Saskatchewan Highway Water and Sewer Renewal

WestLake-Gladstone, Manitoba

completeDrinking WaterSCF
Federal contribution
$100,000
Federal share33%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 3, 2019(actual)
Construction end
Dec 19, 2019(actual)