Expansion of the Yellowhead Regional Rural Water System
Federal contribution
$449,644
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2014
20152016
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Westlake-Gladstone
- Construction start
- Aug 10, 2015(actual)
- Construction end
- Aug 1, 2016(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2015
- Construction end2 months lateforecast May 31, 2016
Also in WestLake-Gladstone