Airport Road Flood Upgrades

Hay River, Northwest Territories

underwayDisaster MitigationDMAF
Federal contribution
$3.6M
$3,631,056
Federal share100%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2025
today
20252026202720282029
BuiltForecast

Approved 9 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
Town of Hay River
Construction start
Feb 1, 2025(actual)
Construction end
Nov 30, 2028(forecast)

Against the original forecast

  • Construction start6 months earlyforecast Aug 1, 2025