Airport Road Flood Upgrades
Hay River, Northwest Territories
Federal contribution
$3.6M
$3,631,056
Federal share100%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 6, 2025
today
20252026202720282029
BuiltForecast
Approved 9 months before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Town of Hay River
- Construction start
- Feb 1, 2025(actual)
- Construction end
- Nov 30, 2028(forecast)
Against the original forecast
- Construction start6 months earlyforecast Aug 1, 2025
Also in Hay River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121284 in the federal list. How to read these figures.