Hay River Community Road Upgrades Improvement
Hay River, Northwest Territories
Federal contribution
$5.6M
$5,630,025
Federal share63%
of $8.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Hay River
- Construction start
- Jul 15, 2020(actual)
- Construction end
- Oct 31, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2020
- Construction end10 months earlyforecast Aug 31, 2023
Also in Hay River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54109 in the federal list. How to read these figures.