Schedule

Announced and approvedAug 13, 2019
2020202120222023
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Hay River
Construction start
Aug 1, 2020(actual)
Construction end
Feb 28, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2020
  • Construction end6 months earlyforecast Aug 28, 2023