Hay River Waste Water Lift Station
Hay River, Northwest Territories
Federal contribution
$4.6M
$4,606,875
Federal share75%
of $6.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2019
2020202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Hay River
- Construction start
- Aug 1, 2020(actual)
- Construction end
- Feb 28, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2020
- Construction end6 months earlyforecast Aug 28, 2023