Water System Upgrades

Saint-Antoine, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$728,270
Federal share33%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2005
200620072008
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Saint-Antoine
Construction start
Jun 23, 2005(actual)
Construction end
Sep 3, 2008(actual)

Against the original forecast

  • Construction end3.1 years lateforecast Aug 15, 2005

Also in Saint-Antoine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12136 in the federal list. How to read these figures.