Water System Upgrades
Federal contribution
$728,270
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 31, 2005
200620072008
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Saint-Antoine
- Construction start
- Jun 23, 2005(actual)
- Construction end
- Sep 3, 2008(actual)
Against the original forecast
- Construction end3.1 years lateforecast Aug 15, 2005
Also in Saint-Antoine
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12136 in the federal list. How to read these figures.